August 2010 – The Cool Dry Conservatory has progressed quickly over the last month and the final arches have been erected. The gridshell has been completed and they have started to remove the external scaffolding. Support hangers between the arches and gridshell and the gridshell bracing are being installed on the Cool Dry. The Cool Moist Conservatory core is rising out of the ground at an alarming rate and monthly visits don’t seem enough to keep up with the speedy rate of construction. Sandwiched between the two conservatories is the Visitor Hub area where builder’s works are moving fast, you can see the construction sequence of the fairfaced concrete elipse-shaped columns in a progression of photos below.